I will be sending more info
about addressing this issue of a "Programmatic EIS" for
the West
Coast soon............ JM
http://www.ferc.gov/press-room/press-releases/2007/2007-1/02-15-07-C-1.asp
| FERC
Press Release: February 15, 2007 |
View
Printable PDF Version |
| Docket
Numbers: CP05-420; CP06-12 CP06-13; CP06-14; CP05-357 &
CP05-357-004; CP06-355 & CP96-810-006; CP06-365 &
CP06-366-001, etc. |
Commission authorizes two new LNG Import
Terminals; expands natural gas energy infrastructure; dismisses
complaint in pending Oregon
LNG proceeding
The Federal Energy Regulatory Commission today approved two new
liquefied natural gas (LNG) terminals that could supply approximately
3.1 billion cubic feet (Bcf) of natural gas per day to meet ever
increasing demand.
FERC Chairman Joseph T. Kelliher observed: “Our natural gas markets
are changing fundamentally. North American natural gas supply is no
longer sufficient to meet North American demand, and LNG will play a
more important role in meeting U.S. natural gas supply needs. These are
significant import projects, with a combined capacity nearly equal to
the projected capacity of an Alaskan gas pipeline. More importantly, we
find that these projects meet our high safety standards.”
After a thorough environmental, security and safety analysis conducted
by staff in cooperation with the U.S. Coast Guard and other federal,
state and local agencies, the Commission granted authorization to two
new onshore LNG terminals that would be located in Jackson County, Mississippi.
The Commission adopted staff’s recommended conditions to its
authorization to mitigate any potential adverse impacts on the
environment.
The projects, which will be located adjacent to one another, are:
- Bayou Casotte Energy LLC
(Docket No. CP05-420) – Commission authorized the construction and
operation of a new onshore Casotte Landing LNG terminal project
proposed by Chevron so that its affiliates may import and deliver up
to a peak volume of 1.6 Bcf of regasified LNG per day. The vaporized
LNG will reach the interstate grid through interconnections with
five interstate pipelines. The project would use a 264-acre parcel
of land adjacent to Chevron’s existing Pascagoula,
Mississippi, oil refinery on Bayou Casotte.
- Gulf LNG Energy LLC and Gulf LNG
Pipeline LLC (Docket Nos.
CP06-12, CP06-13 and CP06-14). The Commission authorized the LNG
Clean Energy Project proposed by Gulf LNG Energy LLC for a new
onshore terminal and related facilities designed to provide a peak
delivery of 1.5 Bcf per day. The project would provide vaporized
natural gas to the interstate grid through a new pipeline that would
connect with two interstate pipelines and a gas processing plant
owned by BP. The estimated $450 million project also would be
located in Pascagoula,
Mississippi.
Also today, the Commission authorized the expansion of a pipeline
proposed by sponsors of the recently authorized Cheniere Creole Trail
LNG project (Docket Nos. CP05-357-003 and CP05-357-004). The Commission
amended its previous authorization and approved the construction and
operation of an additional 18.1 miles of 42-inch pipeline in Cameron
Parish, Louisiana,
that will connect with another recently approved project proposed by
Cheniere Sabine Pass Pipeline LP. The amended proposal would extend
Chienere Trail’s 116.8 mile certificated pipeline system westward from
the Creole Trail’s terminal site to interconnect with the terminus of
the Sabine Pass pipeline system, located at Johnson’s Bayou in Cameron
Parish, in order to access and transport up to 2.0 Bcf per day of
previously authorized regasified LNG originating from the Sabine Pass
LNG terminal.
The amended Creole Trail pipeline project would also connect its
facilities to additional gas suppliers and processing plants located at
Johnson’s Bayou through other various pipeline interconnections with
Sabine Pass. The estimated cost of the project is $101.7 million.
Also today, the Commission authorized Maritimes & Northeast
Pipelines LLC (Docket Nos. CP06-355-000, CP06-355-001 &
CP96-810-006) to expand its existing facilities to increase its mainline
design capacity by approximately 418,000 dekatherms per day to 833,317
dekatherms per day to accommodate the importation of regasified LNG from
the Canaport LNG import terminal in Canada
to supply the U.S. Northeast.
In its Phase IV Pipeline Project, Maritimes proposes to construct and
operate an additional 1.7 miles of 30-inch diameter pipeline loop,
adjacent to its existing 30-inch diameter mainline, that will extend
from the St. Croix River at the U.S.-Canada border to its Baileyville,
Maine, compressor station. In addition, Maritimes proposes to
construct and operate five new compressor station units with a total of
89,864 horsepower at Woodchopping Ridge, Brewer, Searsmont, Westbrook
and Eliot in Maine,
along with either new or upgraded metering stations located along its
route in Maine.
The Commission also approved Maritimes’ request to amend its
Presidential Permit to permit the increased imported volumes of natural
gas from Canada
and to construct and operate an additional interconnection at the
U.S.-Canada border near Goldboro,
Nova Scotia. The proposed project will cost an estimated $321.3
million.
In another proceeding, the Commission dismissed a complaint alleging
FERC Staff violated ex parte contact prohibition rules by
attending a December 14, 2006 meeting on environmental issues relating
to Northern Star Energy LLC’s proposed Bradwood Landing LNG Project,
currently under FERC Staff review (Docket No. CP06-365-001,
CP06-366-001, CP06-376-001 and CP06-377-001). Complainants alleged FERC
Staff should not have attended the meeting that included representatives
from Bradwood Landing, Northern Star, the U.S. Army Corps of Engineers,
the U.S. Coast Guard, the U.S. Department of Commerce’s National
Marine Fisheries Service, the Nez Perce Tribe, Columbia River
Inter-Tribal Fish Commission, and others.
Northern Star filed an application on June 5, 2006 to construct and
operate an onshore import LNG terminal and a send-out pipeline that
would import up to 1Bcf of gas per day. The project would be located in
Bradwood, Clatsop County, OR. In addition, the company proposes to
construct and operate a 34-mile long Bradwood Landing Pipeline that
would transport the LNG from the terminal to Northwest Pipeline Corp’s
pipeline in Cowlitz,
Washington for service to interstate markets.
The Commission found FERC Staff properly adhered to procedures and
followed FERC regulations covered by Section 385.2201(e)(vi)(A), which
permits off-the-record communications for the purpose of preparing an
environmental impact statement (EIS) as long as a summary of the
communications is promptly placed in the public record.
“Such was the procedure followed in this case, where written and oral
off-the record communications relating to the preparation of an EIS were
promptly placed in the decisional record of the proceeding and noticed
by the Secretary. Complainants will have an opportunity to review and
comment on the information presented and discussed at the December 14,
2006 meeting, and their comments will be taken into account by the
Commission as part of its preparation of its EIS,” the Commission
said.
R-07-11