|
|
|
|
The
tangles of government bureaucracy and information sharing have delayed the
application process for a liquefied natural gas import terminal in Coos
County .
According to Bob Braddock, project manager of Jordan Cove Energy Project,
the LNG company now plans to file its application with the Federal Energy
Regulation Commission by April 2. The original deadline of Jan. 31 was
pushed back, he said, because of the slow nature of working with the
federal agency.
“It's a catch-22. We couldn't file our second draft resource reports
until we received comments from the agency and we didn't get some of those
back until December,” he said.
FERC project manager Paul Friedman said his agency requires a 60-day
window after receiving the last second draft report before a company can
file its final application.
“We need to be able to review their documents and make sure all the data
we need is included,” he said.
To complicate matters, Jordan Cove has been coordinating its filing date
with Williams, the company proposing the Pacific Connector Gas Pipeline.
Despite some delays in the collecting of soil samples from the Coos Bay
estuary, Williams was able to complete its forms on Dec. 18.
Michele
Swaner, a communications specialist with Williams, said the company had
anticipated delays in collecting boring samples from Coos Bay to determine
an underwater route.
“We built enough time into our plans for those contingencies,” with
drilling delays, she said.
Braddock said Jordan Cove expects to submit its final resource report this
week.
Compiling an application
|
|
|
|
Rather
than logistical logjams in Coos Bay , delays have primarily developed in Washington
, D.C. , and an unexpected death temporarily left a state
department scrambling in Salem .
In January 2006, with several LNG terminals proposed throughout the state,
Gov. Ted Kulongoski designated the Department of Energy as the lead state
agency in working with FERC. An analyst in the department, Cathy Van Horn,
was given the task of working on a couple of the proposed terminal
projects, including Jordan Cove. Practically all state comments on Jordan
Cove resource reports went across Van Horn's desk first.
On Sept. 15, the 45-year-old Van Horn died.
“It was so traumatic and completely unexpected,” said Diana Enright,
an assistant director in the department.
Despite the setback, Braddock said, the state handled the situation
admirably, continuing to process paperwork and respond to Jordan Cove's
concerns.
More significant, in Braddock's estimation, were bottlenecks produced by
governmental agencies along the Potomac River . As an example, Braddock
noted how he was expecting some documents from the Bureau of Land
Management in late November.
“For some reason, they did not pop up on time,” he said.
Braddock also noted that revisions he had scheduled to complete by
December were delayed because many federal employees exercised their
vacation days and were unable to review documents.
Such scenarios are just part of the terrain when dealing with the federal
government, he said.
“I've always stated that the dates we give are the earliest possible and
most likely not achievable. There have been good reasons for the delays on
both sides.”
Jordan Cove and Williams will spend much of the remaining two plus months
before the April deadline fine-tuning their applications.
“FERC will send out data requests and comments from state agencies,
local residents and stakeholders,” said Troy Ruflin, the Pacific
Connector pipeline project manager. “Basically, we will be filling in
the gaps that remain in our resource reports.”
One of the more mundane aspects of the revisions, Braddock said, is
ensuring that terminology is consistent throughout the application
document. Since numerous contractors are employed by both groups to
collect environmental information, some terms are used differently from
field to field. Before the application is submitted, all such
discrepancies must be aligned.
“It's not so much content but language,” he said. “For example, we
will use the term terminal in the document, not regasification terminal.
Also, there is the difference between ship and vessel. It may seem like a
minor detail, but it is one thing we need to take care of.”
It also constitutes a sizable undertaking. When the final application is
completed, Braddock estimates the document would take up about 10 feet of
space on a bookshelf.
Next stage
This week, representatives from both companies will put aside their
proofreading and assemble for a series of FERC-sponsored informational
meetings. Unlike recent public forums put together by local residents, the
proponents, as well as their opponents, will primarily be on hand to
listen. The purpose of the meeting will be to discuss the next stage in
the FERC process.
“The meeting is designed to let people know how (various government
agencies) do their environmental reviews,” said Friedman from Washington
. “It is not intended as a public input meeting. It is to let people
know what is going on.”